Building Renovation Update #3 - 30 Nov 2017

Professor Stephen Bottomley and Di Stewart visit the 2017 ANU College of Law renovation site.

Dear Staff,

What has happened this week and what to expect next week.

What has happened this week

  • Ceiling and walls stripped out
  • Scaffolding

Next week you can expect

  • Scaffolding (hammering metal on metal noise)
  • Saw cutting of brick walls
  • Jack hammering
  • Floor grinding
  • Preparation for and possibly demolition of old NJCA building

There will be noise, vibration and dust.

If you have any questions, please ask me.

Regards, Cris